Mannat Tower
by Shri Sati Builders and Developers Private Limited
CTS No 118pt 119pt 121 to 125 126pt 129pt 155pt, Kurla, 400075
- 21 appeals at MahaREAT. 21 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~1 yr. Originally promised Dec 2017, now proposed Mar 2019 per the RERA filing.
- 64 RERA complaints. 64 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 54.5%.
Where it is · CTS No 118pt 119pt 121 to 125 126pt 129pt 155pt, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800009212
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2019originally December 2017
- Construction
- 54.5% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.