MARATHON EMBLEM-2
764/4A/1, 764/4A/2, Kurla, 400080
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 45%.
- Promised amenities not started. Gymnasium is at 0% build with possession due Dec 2021 per the RERA filing.
Where it is · 764/4A/1, 764/4A/2, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800000556
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 45% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.