Under construction
MARATHON NAGARI NX VIGO D
MahaRERA P51700005045High risk
79/3PT. 83/10PT., SHIRGAON, 421503
Post your property hereOwn or renting out a unit in MARATHON NAGARI NX VIGO D? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in SHIRGAON come to you.
Dec 2020
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
Satellite view of this address
Where it is · 79/3PT. 83/10PT., SHIRGAON
Promoter
Builder profile
MARATHON REALTY PVT LTD
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700005045
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in SHIRGAON
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NAV SAI CHHAYA CHS LTD
SHIRGAON100% builtPoss. January 20201 complaint
KALP NISARG
SHIRGAON90.9% builtPoss. March 2022
Mohan Willows Commercial
SHIRGAON90.9% builtPoss. March 2022
SHREEJI ICONIC PHASE II
SHIRGAON90.9% builtPoss. November 2022
NUTAN OMKAR VIHAR
SHIRGAON84.1% builtPoss. August 2022
Sai Vedant
SHIRGAON83.5% builtPoss. March 2027
ALOK GALAXY
SHIRGAON81.8% builtPoss. December 2026
SILVER PRIDE
SHIRGAON81.8% builtPoss. June 2024
Keep exploring
Where this project sits, who built it, and how SHIRGAON compares.
In SHIRGAON
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.