MARATHON NEXWORLD AURA-1
by MATRIX ENCLAVES PROJECTS DEV. PVT. LTD
22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/1, 30/1, 30/2, 80, Betawade Gaon, 400612
- 22 appeals at MahaREAT. 22 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- 32 RERA complaints. 32 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 46.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Where it is · 22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/1, 30/1, 30/2, 80, Betawade Gaon
Area guide
What it's like to buy in Betawade Gaon
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700000652
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2023originally December 2022
- Construction
- 46.5% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Betawade Gaon compares.
In Betawade Gaon
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.