Maruti Bhuvan
by Suresh Prabhushankar Sharma
135, 135 1 to 12 , 136, 136 1 to 19 , New CTS No. 135A, Mogra, 400069
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~5 yrs. Originally promised Mar 2019, now proposed Mar 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 72.7%.
Where it is · 135, 135 1 to 12 , 136, 136 1 to 19 , New CTS No. 135A, Mogra
Area guide
What it's like to buy in Mogra
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Office corridors (SEEPZ, MIDC) with value housing pockets between them.
- Growth drivers:
- Airport proximity, Metro 1/7, IT-park employment.
- Who buys here:
- Working couples prioritising commute over frills.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800005335
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2024originally March 2019
- Construction
- 72.7% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Mogra compares.
In Mogra
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.