🏗️
Under construction
MAULI SHANKAR KRUPA
MahaRERA P52100013080High risk
CTS No 224,276,277,278,673, Baramati (M Cl), 413102
Post your property hereOwn or renting out a unit in MAULI SHANKAR KRUPA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Baramati (M Cl) come to you.
Sept 2020
Possession
34.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 34.5%.
Satellite view of this address
Where it is · CTS No 224,276,277,278,673, Baramati (M Cl)
Promoter
Builder profile
Badri Construction
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100013080
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2020
- Construction
- 34.5% complete
- Units sold
- 0 of 0
Similar projects in Baramati (M Cl)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHINDE PARK
Baramati (M Cl)Poss. August 2018
KRUPASINDHU CLASSIC
Baramati (M Cl)Poss. June 2027
Renuka Pride
Baramati (M Cl)100% builtPoss. December 2017
SAIDHAM
Baramati (M Cl)90.9% builtPoss. October 2021
PANDURANG PRESTIGE POINT PHASE 1
Baramati (M Cl)90.9% builtPoss. January 2019
SAI SADAN RESIDENCY 1
Baramati (M Cl)90.9% builtPoss. June 2019
CHINTAMANI COMPLEX
Baramati (M Cl)90.9% builtPoss. December 2018
SANSKRUTI RESIDENCY
Baramati (M Cl)90.9% builtPoss. January 2021
Keep exploring
Where this project sits, who built it, and how Baramati (M Cl) compares.
In Baramati (M Cl)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.