MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27
SNO195H1P 195H2P 213P 214P 215P 216P 224H1P 224H2P, Virar West, 401303
- Mortgaged to a lender (₹155 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹155 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~3 yrs. Originally promised Mar 2027, now proposed Dec 2029 per the RERA filing.
Where it is · SNO195H1P 195H2P 213P 214P 215P 216P 224H1P 224H2P, Virar West
Area guide
What it's like to buy in Virar West
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000034708
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2029originally March 2027
- Construction
- 35.7% complete
- Units sold
- 318 of 901
Similar projects in Virar West
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Virar West compares.
In Virar West
The developer
Research