High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 288A HISSA 1/2PT 288A HISSA 3, VIRAR WEST

Area guide

What it's like to buy in VIRAR WEST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M K & BROTHERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
ENCON

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000007416
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2021
Construction
82.3% complete
Units sold
8 of 31

Similar projects in VIRAR WEST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how VIRAR WEST compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.