Under construction
Mayuri Infinity
MahaRERA P52100015703High risk
27 4, TATA inora park, 411028
Post your property hereOwn or renting out a unit in Mayuri Infinity? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TATA inora park come to you.
Apr 2024
Possession
66.7%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Apr 2021, now proposed Apr 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Apr 2024) has passed with construction at 66.7%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2024 per the RERA filing.
Satellite view of this address
Where it is · 27 4, TATA inora park
Promoter
Builder profile
MAYURI LANDMARKSLLP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100015703
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2024originally April 2021
- Construction
- 66.7% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how TATA inora park compares.
In TATA inora park
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.