High risk
  • Possession delayed ~3 yrs. Originally promised Apr 2021, now proposed Apr 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2024) has passed with construction at 66.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2024 per the RERA filing.
Satellite view of this address

Where it is · 27 4, TATA inora park

Promoter

Builder profile

Builder
MAYURI LANDMARKSLLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100015703
Status
New
Stage
Certificate Signed
Possession
April 2024originally April 2021
Construction
66.7% complete