Mar 2027
Possession
83.6%
Built
0
Complaints
77
Units
Caution
- Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Mar 2027 per the RERA filing.
Satellite view of this address
Where it is · Plot 3 Sub Plot J, New Panvel (W)
Promoter
Builder profile
MAZAGON DOCK NIVARA CO-OP HSG SOC LTD
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
DESTINATION ARCHITECTURE INTERIOR DESIGNS
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52000047201
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally September 2024
- Construction
- 83.6% complete
- Units sold
- 50 of 77
Similar projects in New Panvel (W)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SADGURU UNIVERSAL
New Panvel (W)100% builtPoss. December 2022
ALLIANCE
New Panvel (W)100% builtPoss. May 2023
MAZAGAON DOCK SAI CO-OP HSG SOC LTD
New Panvel (W)100% builtPoss. January 2025
MAZAGON DOCK MANDAR CO-OP. HSG.SOC.LTD.
New Panvel (W)68.6% builtPoss. January 2027
DDSR ANUPARVA CO-OPERATIVE HOUSING SOCIETY LIMITED
New Panvel (W)28.2% builtPoss. December 2027
Keep exploring
Where this project sits, who built it, and how New Panvel (W) compares.
In New Panvel (W)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.