Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · 254-D, Andheri west

Area guide

What it's like to buy in Andheri west

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Fortune Investments

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
CHIRAG S. RAYANI

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800048471
Status
New
Stage
Certificate Signed
Possession
July 2027originally December 2025
Construction
66.8% complete
Units sold
18 of 82

Similar projects in Andheri west

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri west compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.