High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 310 AND 311 AND 312, KOLAD

Area guide

What it's like to buy in KOLAD

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MEGHNA BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DHARMESH V BHALANI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52000009526
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
90.9% complete
Units sold
126 of 178