- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 75%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.
Where it is · SURVEY NO 90/1 PART, MOHAMMADWADI PUNE
Area guide
What it's like to buy in MOHAMMADWADI PUNE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100023691
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 75% complete
- Units sold
- 0 of 0
Similar projects in MOHAMMADWADI PUNE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how MOHAMMADWADI PUNE compares.
In MOHAMMADWADI PUNE
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.