Under construction

MIDORI TOWER PHASE 2

MahaRERA P52100025516High risk

by VIKRAM DEVELOPERS AND PROMOTERS

SURVEY NO 14 PART , 15 PART AND 16 PART , PIMPLE NILAKH, Haveli, 411027

Official record
Jan 2028
Possession
55.6%
Built
1
Complaints
108
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2026, now proposed Jan 2028 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2028 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 14 PART , 15 PART AND 16 PART , PIMPLE NILAKH, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
VIKRAM DEVELOPERS AND PROMOTERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
ANA CONSORTIUM PVT LTD

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100025516
Status
New
Stage
Certificate Signed
Possession
January 2028originally September 2026
Construction
55.6% complete
Units sold
82 of 108

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.