Under construction
Milan Bliss
MahaRERA P51800046482High risk
by Milan Interbuilt Private Limited
621(pt), 621/4 to 7, Andheri, 400069
Post your property hereOwn or renting out a unit in Milan Bliss? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Andheri come to you.
Aug 2025
Possession
60.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 60.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2025 per the RERA filing.
Promoter
Builder profile
Milan Interbuilt Private Limited
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800046482
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2025originally February 2025
- Construction
- 60.5% complete
- Units sold
- 0 of 0
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ROYAL GREEN
AndheriPoss. December 20265 complaints
MARVEL PRIDE
AndheriPoss. February 20285 complaints
Plotted Development Scheme at Sindhudurhnagari, Oras, Tal- Kudal, Dist- Sindhudurg
AndheriPoss. December 2017
Pearl 2
AndheriPoss. March 20272 complaints
AMRUT TARA
AndheriPoss. March 2027
Grace Grandeur
AndheriPoss. August 20272 complaints
SHIVDHAM
AndheriPoss. December 2025
VALLETTA
AndheriPoss. January 20271 complaint
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.