High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 66.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.

Promoter

Builder profile

Builder
MILE STONE DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100030586
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
66.4% complete
Units sold
0 of 0