Under construction

MIravet District Phase - I

MahaRERA P52100030203High risk

by AUM DEVELOPERS

S.No. 100/1/1, 100/1/2, 101/1, 149/1/A, 150/1, 150/2/1, 150/2/2A, at Ravet, Mhaske Wasti, Ravet, 412101

Official record
Dec 2026
Possession
92.3%
Built
3
Complaints
406
Units
High risk
  • Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
  • Mortgaged to a lender (₹12 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹12 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · S.No. 100/1/1, 100/1/2, 101/1, 149/1/A, 150/1, 150/2/1, 150/2/2A, at Ravet, Mhaske Wasti, Ravet

Area guide

What it's like to buy in Mhaske Wasti

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AUM DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Prakash Kulkarni

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100030203
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
92.3% complete
Units sold
368 of 406

Keep exploring

Where this project sits, who built it, and how Mhaske Wasti, Ravet compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.