Under construction

Mohan Suburbia III

MahaRERA P51700021395High risk

by MOHAN LIFESPACES LLP

25/10,25/11,25/12,35/2,36/3to36/15,36/16p,37,39/2,178,25/13, Khoj Kuntawli, 421501

Official record
Aug 2023
Possession
90.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jun 2022, now proposed Aug 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 90.5%.
Satellite view of this address

Where it is · 25/10,25/11,25/12,35/2,36/3to36/15,36/16p,37,39/2,178,25/13, Khoj Kuntawli

Area guide

What it's like to buy in Khoj Kuntawli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MOHAN LIFESPACES LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700021395
Status
New
Stage
Certificate Signed
Possession
August 2023originally June 2022
Construction
90.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Khoj Kuntawli compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.