MONTAG GREENS
by MONTAG INFRASTRUCTURE PRIVATE LIMITED
SURVEY NO.19 HISSA NO.8, Pokharkarwadi, 410201
- 5 appeals at MahaREAT. 5 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~10 yrs. Originally promised Dec 2018, now proposed Dec 2028 per the RERA filing.
- 16 RERA complaints. 16 complaint records are disclosed against this project on MahaRERA.
Where it is · SURVEY NO.19 HISSA NO.8, Pokharkarwadi
Area guide
What it's like to buy in Pokharkarwadi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000011050
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2028originally December 2018
- Construction
- 95.6% complete
- Units sold
- 66 of 154
Keep exploring
Where this project sits, who built it, and how Pokharkarwadi compares.
In Pokharkarwadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.