MONTECITO PHASE I - D BUILDING PART 2
S. No. 86/1/1/2, C.T.S. No. 2024 part, Sahakar Nagar Parvati, Parvati, 411009
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- 16 RERA complaints. 16 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 86.9%.
- Promised amenities not started. Swimming Pool, Landscaped Garden, Kids Play Area are at 0% build with possession due Dec 2018 per the RERA filing.
Where it is · S. No. 86/1/1/2, C.T.S. No. 2024 part, Sahakar Nagar Parvati, Parvati
Area guide
What it's like to buy in Parvati
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100008717
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2018
- Construction
- 86.9% complete
- Units sold
- 0 of 0
Similar projects in Parvati
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Parvati compares.
In Parvati
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.