High risk
  • Possession delayed ~3 yrs. Originally promised Apr 2024, now proposed Aug 2027 per the RERA filing.
  • Behind schedule. Possession is due Aug 2027 but construction is only at 39.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2027 per the RERA filing.

Promoter

Builder profile

Builder
Sumit Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700023720
Status
Ongoing
Stage
Certificate Signed
Possession
August 2027originally April 2024
Construction
39.8% complete
Units sold
0 of 0

Similar projects in Murbad

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Murbad compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.