High risk
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project — the strongest enforcement action on record.
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.
  • 38 RERA complaints. 38 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · F P No 106, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Thane (Ghodbunder belt)Mid-income

A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
MORYA INFRACONSTRUCT PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700005511
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2024
Construction
90.9% complete
Units sold
173 of 255

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.