High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~4 yrs. Originally promised Jun 2021, now proposed Mar 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 59.5%.
Satellite view of this address

Where it is · S No 47-1 47-1A 47-3-1 47-4, Ambegaon

Promoter

Builder profile

Builder
Mind Space Realty Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100008615
Status
Ongoing
Stage
Certificate Signed
Possession
March 2025originally June 2021
Construction
59.5% complete
Units sold
0 of 0

Similar projects in Ambegaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ambegaon compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.