Under construction
MUNISH SMRITI
MahaRERA P99000009677High risk
by SMRITI INFRAHEIGHTS PRIVATE LIMITED
S. NO. 12, H.NO. 7, Vasai-Virar City (M Corp), 401208
Post your property hereOwn or renting out a unit in MUNISH SMRITI? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Vasai-Virar City (M Corp) come to you.
Dec 2020
Possession
9.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 9.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Satellite view of this address
Where it is · S. NO. 12, H.NO. 7, Vasai-Virar City (M Corp)
Promoter
Builder profile
SMRITI INFRAHEIGHTS PRIVATE LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000009677
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 9.1% complete
- Units sold
- 0 of 0
Similar projects in Vasai-Virar City (M Corp)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Musavvir Residency
Vasai-Virar City (M Corp)Poss. December 2030
SHAIKH RESIDENCY
Vasai-Virar City (M Corp)Poss. March 2030
VIDYA APARTMENT
Vasai-Virar City (M Corp)Poss. March 2028
Flora (Building no 07 - Wing A)
Vasai-Virar City (M Corp)Poss. December 2028
Dharti 5
Vasai-Virar City (M Corp)Poss. December 2028
MUNISH SMRITI
Vasai-Virar City (M Corp)100% builtPoss. December 2020
Virar Bolinj Yogiraj CHS Ltd
Vasai-Virar City (M Corp)90.9% builtPoss. January 2024
KUMKUM Sector 7 Building 23 Wing F
Vasai-Virar City (M Corp)90.9% builtPoss. July 2023
Keep exploring
Where this project sits, who built it, and how Vasai-Virar City (M Corp) compares.
In Vasai-Virar City (M Corp)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.