Munisuvrat Arc - Building 1 Plot 1 and Munisuvrat Royal - Building 2 on Plot 2
126/3P, 126/4P, 161/3/1APt, 161/3/1B, Bhiwandi, 421302
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 57.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2019 per the RERA filing.
Where it is · 126/3P, 126/4P, 161/3/1APt, 161/3/1B, Bhiwandi
Area guide
What it's like to buy in Bhiwandi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700004825
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2019
- Construction
- 57.3% complete
- Units sold
- 0 of 0
Similar projects in Bhiwandi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Bhiwandi compares.
In Bhiwandi
The developer
Research