Under construction
NAATH RESIDENCY C WING
MahaRERA P52100017731High risk
GAT NO. 194 SURVEY NO. 43 1 6, MOSHI, 412105
Post your property hereOwn or renting out a unit in NAATH RESIDENCY C WING? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MOSHI come to you.
Nov 2020
Possession
36.4%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 36.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2020 per the RERA filing.
Area guide
What it's like to buy in MOSHI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
NAVNATH DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100017731
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2020
- Construction
- 36.4% complete
- Units sold
- 0 of 0
Similar projects in MOSHI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SPRINGS
MOSHIPoss. March 2029
STELLA
MOSHI100% builtPoss. February 20192 complaints
AISHWARYAM HAMARA PHASE II
MOSHI100% builtPoss. March 2023
SHRI GANESHA HEIGHTS
MOSHI100% builtPoss. June 2024
Samarth Classic
MOSHI100% builtPoss. December 2026
Sai Hira
MOSHI90.9% builtPoss. December 2019
Kamalraj Datta Vihar A Bldng
MOSHI90.9% builtPoss. December 2021
Orbit Bonneville
MOSHI90.9% builtPoss. December 2019
Keep exploring
Where this project sits, who built it, and how MOSHI compares.
In MOSHI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.