Under construction

Nakshatra Heights

MahaRERA P52000051059High risk

by Sharvari Enterprises

1271,1272,1273,1274,1275,1276,1277,1278,1279,1318, Ziral Ali, 402107

Official record
Oct 2027
Possession
65.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jun 2026, now proposed Oct 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · 1271,1272,1273,1274,1275,1276,1277,1278,1279,1318, Ziral Ali

Promoter

Builder profile

Builder
Sharvari Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000051059
Status
New
Stage
Certificate Signed
Possession
October 2027originally June 2026
Construction
65.5% complete
Units sold
0 of 0