High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 49.3%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.
Satellite view of this address

Where it is · 267 PART AND 268 PART, DHANSAR

Promoter

Builder profile

Builder
Shreemangal Infra

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000019071
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
49.3% complete
Units sold
0 of 0

Similar projects in DHANSAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how DHANSAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.