NANDAN CARNIVAL A BUILDING
GAT NO 39 TO 49, ADGAON, 422003
- Mortgaged to a lender (₹80 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹80 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Mar 2028 per the RERA filing.
Where it is · GAT NO 39 TO 49, ADGAON
Area guide
What it's like to buy in ADGAON
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Metro-1 anchor with Godrej's Vikhroli land bank next door.
- Growth drivers:
- Metro 1 interchange, Eastern Express Highway, corporate campuses.
- Who buys here:
- Families wanting east-side connectivity to BKC/Fort.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51600012372
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2028originally December 2019
- Construction
- 64.4% complete
- Units sold
- 9 of 104
Similar projects in ADGAON
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how ADGAON compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.