Dec 2021
Possession
39%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 39%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2021 per the RERA filing.
Satellite view of this address
Where it is · SURVEY NO.34,, AMBEGAON BK
Promoter
Builder profile
SAI SANKALP DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100014132
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally March 2021
- Construction
- 39% complete
- Units sold
- 0 of 0
Similar projects in AMBEGAON BK
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VARAD DWARKA
AMBEGAON BKPoss. April 2029
SHIVAY CONSTRUCTION
AMBEGAON BK100% builtPoss. December 2025
VIDYANNAD
AMBEGAON BK90.9% builtPoss. March 2023
SHREE SADGURU CHHAYA
AMBEGAON BK81.8% builtPoss. December 2023
SAI GANESH
AMBEGAON BK81.8% builtPoss. March 2026
YASHODA COMPLEX
AMBEGAON BK81.4% builtPoss. December 2024
VASTUDEEP AVENUE
AMBEGAON BK77.5% builtPoss. December 2026
ADISHREE
AMBEGAON BK65.9% builtPoss. September 2023
Keep exploring
Where this project sits, who built it, and how AMBEGAON BK compares.
In AMBEGAON BK
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.