- Possession delayed ~3 yrs. Originally promised Sept 2021, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 95.5%.
Where it is · GAT NO. 1460, Haveli
Area guide
What it's like to buy in Haveli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Bandra's quieter northern neighbour — low-rise lanes going boutique.
- Growth drivers:
- Society redevelopment, airport and BKC equidistance.
- Who buys here:
- Professionals wanting Bandra adjacency with less noise.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100008374
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally September 2021
- Construction
- 95.5% complete
- Units sold
- 0 of 0
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Haveli compares.
In Haveli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.