High risk
  • Possession delayed ~2 yrs. Originally promised Sept 2019, now proposed Mar 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.
Satellite view of this address

Where it is · Gut no 152, GORHE BDK

Area guide

What it's like to buy in GORHE BDK

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vile Parle East / AirportUpper-mid

Institutional belt (colleges, airport) with steady society redevelopment.

Growth drivers:
Airport economy, Metro 3, education cluster.
Who buys here:
Airline/airport professionals, Parle loyalists.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Nagarkar Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100006429
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally September 2019
Construction
90.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how GORHE BDK compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.