High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 79.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address

Where it is · SECTOR NO 11, PLOT NO 148 D, NEAR TULSI LANDMARK

Area guide

What it's like to buy in NEAR TULSI LANDMARK

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHEKHAR INFRATECH

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100052677
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
79.8% complete
Units sold
115 of 179

Keep exploring

Where this project sits, who built it, and how NEAR TULSI LANDMARK compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.