Under construction
NEELKANTH MAJESTIC
MahaRERA P52000019595High risk
PLOT NO. 95, SECTOR-18PT, ULWE, PANVEL-410206, ULAWE, 410206
Post your property hereOwn or renting out a unit in NEELKANTH MAJESTIC? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in ULAWE come to you.
Dec 2023
Possession
44.2%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 44.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Area guide
What it's like to buy in ULAWE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
MAHAVIR DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000019595
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023
- Construction
- 44.2% complete
- Units sold
- 0 of 0
Similar projects in ULAWE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
RSM ATHENA
ULAWE100% builtPoss. September 2020
UNIMONT SAPPHIRE
ULAWE100% builtPoss. June 20212 complaints
PLATINUM EMPORIUS
ULAWE100% builtPoss. December 20221 complaint
BHAKTI AURA
ULAWE100% builtPoss. December 2025
SHREEJI COTTAGE
ULAWE100% builtPoss. March 2024
Welkin Star
ULAWE90.9% builtPoss. December 2017
LUCKY CORAL
ULAWE90.9% builtPoss. December 2021
REDDYS CROWN
ULAWE71.8% builtPoss. December 2026
Keep exploring
Where this project sits, who built it, and how ULAWE compares.
In ULAWE
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.