NEELKANTH VIHAR PHASE I
195/2,196,197,200,201/1, NEW PANVEL, 410206
- 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~1 yr. Originally promised Sept 2019, now proposed Nov 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 56.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2020 per the RERA filing.
Where it is · 195/2,196,197,200,201/1, NEW PANVEL
Area guide
What it's like to buy in NEW PANVEL
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000005312
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2020originally September 2019
- Construction
- 56.8% complete
- Units sold
- 0 of 0
Similar projects in NEW PANVEL
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how NEW PANVEL compares.
In NEW PANVEL
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.