🏗️
Under construction

NEHRU NAGAR AMRAPALI CHS LTD

MahaRERA P51800012607High risk

by SAMRUDDHI DEVELOPERS

Survey No.229 267 CTS 2 PART, Kurla, 400024

Official record
Dec 2018
Possession
85%
Built
16
Complaints
0
Units
High risk
  • 16 RERA complaints. 16 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 85%.
Satellite view of this address

Where it is · Survey No.229 267 CTS 2 PART, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SAMRUDDHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800012607
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
85% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.