Under construction
NEON
MahaRERA P52100030290High risk
by YASHCON URBAN DEVELOPMENT LLP
214/1/4, LOHEGAON, 411047
Post your property hereOwn or renting out a unit in NEON? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in LOHEGAON come to you.
Jul 2025
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
- Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 90.9%.
Promoter
Builder profile
YASHCON URBAN DEVELOPMENT LLP
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100030290
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in LOHEGAON
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NAMAY RESIDENCY
LOHEGAON136% builtPoss. December 2027
RAGA
LOHEGAON90.5% builtPoss. September 2022
TINGRE ELITE PHASE 1
LOHEGAON89.1% builtPoss. December 2026
10 BIZ PARK
LOHEGAON82.3% builtPoss. August 2024
SANSKRUTI HOMES
LOHEGAON81.8% builtPoss. December 2019
AAIJI DHAM BUILDING A
LOHEGAON81.8% builtPoss. November 2020
NYATI EMPRESS
LOHEGAON81.8% builtPoss. September 2024
AAIJI DHAM BUILDING B
LOHEGAON72.7% builtPoss. November 2020
Keep exploring
Where this project sits, who built it, and how LOHEGAON compares.
In LOHEGAON
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.