NEW LAXMI CHHAYA
1660 , 1661, Andheri, 400054
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~4 yrs. Originally promised Jul 2019, now proposed Jun 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 90.9%.
Where it is · 1660 , 1661, Andheri
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Bandra's quieter northern neighbour — low-rise lanes going boutique.
- Growth drivers:
- Society redevelopment, airport and BKC equidistance.
- Who buys here:
- Professionals wanting Bandra adjacency with less noise.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800009399
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally July 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.