High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2024, now proposed Jan 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2026) has passed with construction at 90.9%.
Satellite view of this address

Where it is · GAT NUMBER 79 PART, BORHADEWADI, Borhadewadi

Promoter

Builder profile

Builder
Nexus Buildwell

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Unusual Spaces

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100032575
Status
New
Stage
Certificate Signed
Possession
January 2026originally June 2024
Construction
90.9% complete
Units sold
97 of 104

Similar projects in Borhadewadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borhadewadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.