High risk
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 52.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2023 per the RERA filing.
Satellite view of this address

Where it is · 171/2, JAITALA

Promoter

Builder profile

Builder
ANNAPURNA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50500015526
Status
New
Stage
Certificate Signed
Possession
February 2023originally February 2022
Construction
52.3% complete
Units sold
0 of 0

Similar projects in JAITALA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how JAITALA compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.