High risk
- Possession delayed ~2 yrs. Originally promised Oct 2020, now proposed Jul 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 83.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2022 per the RERA filing.
Satellite view of this address
Where it is · 94P, Pimpri
Promoter
Builder profile
Fortune Elite
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100013565
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2022originally October 2020
- Construction
- 83.2% complete
- Units sold
- 0 of 0
Similar projects in Pimpri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Sukhwani Capital Square
PimpriPoss. September 2031
PRASUN SRISHTI
PimpriPoss. December 2029
SONIGARA SUNVIEW D
PimpriPoss. July 2028
SAMRUDDHI RISE
PimpriPoss. December 2029
SHUBHASHREE
Pimpri100% builtPoss. June 2019
Centralis Tower 1
Pimpri100% builtPoss. August 20231 complaint
Centralis Tower 3
Pimpri100% builtPoss. March 20232 complaints
Pradhan Mantri Awas Yojana-Pimpri R. No 77
Pimpri100% builtPoss. November 2023
Keep exploring
Where this project sits, who built it, and how Pimpri compares.
In Pimpri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.