Under construction

NISHIGANDHA PARK PHASE 1

MahaRERA P52100005610High risk

by M/S ARCHWAY ESTATES

S.NO129 PLOT NO. 32 IDEAL COLONY, Kothrud, 411038

Official record
Dec 2022
Possession
61.4%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2018, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 61.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · S.NO129 PLOT NO. 32 IDEAL COLONY, Kothrud

Promoter

Builder profile

Builder
M/S ARCHWAY ESTATES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100005610
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally December 2018
Construction
61.4% complete
Units sold
0 of 0

Similar projects in Kothrud

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kothrud compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.