High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
OSTWAL AND PATADIA VENTURE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700047533
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
27.3% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.