OAK STERLING VISTA
MOUZA AND KHASRA ZINGABAI TAKLI 248/2, MOUZA ZINGABAI TAKLI, 440013
- Mortgaged to a lender (₹18 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹18 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~1 yr. Originally promised Dec 2026, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Where it is · MOUZA AND KHASRA ZINGABAI TAKLI 248/2, MOUZA ZINGABAI TAKLI
Area guide
What it's like to buy in MOUZA ZINGABAI TAKLI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P50500055834
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally December 2026
- Construction
- 34% complete
- Units sold
- 17 of 133
Keep exploring
Where this project sits, who built it, and how MOUZA ZINGABAI TAKLI compares.
In MOUZA ZINGABAI TAKLI
The developer
Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.