Under construction

OLYMPIA PHASE 1

MahaRERA P52100009480High risk

by OXFORD INFRA GROUP

S NO 121/3, BHUMKAR CHOWK WAKAD, Wakad, 411057

Official record
Dec 2022
Possession
52.3%
Built
15
Complaints
0
Units
High risk
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Dec 2018, now proposed Dec 2022 per the RERA filing.
  • 15 RERA complaints. 15 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 52.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · S NO 121/3, BHUMKAR CHOWK WAKAD, Wakad

Area guide

What it's like to buy in Wakad

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
OXFORD INFRA GROUP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100009480
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally December 2018
Construction
52.3% complete
Units sold
0 of 0

Similar projects in Wakad

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Wakad compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.