OM RESIDENCY
66/3/1, adharwadi, 421301
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 0%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Where it is · 66/3/1, adharwadi
Area guide
What it's like to buy in adharwadi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central-line volume market — affordable towers around busy junctions.
- Growth drivers:
- Metro 5, ring-road plans, the region's most accessible pricing.
- Who buys here:
- Budget-first buyers who commute the central line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700009448
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally June 2021
- Construction
- 0% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how adharwadi compares.
In adharwadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.