Caution
  • Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 81.8%.
Satellite view of this address

Where it is · S NO 115/1A PLOT NO 24, KUPWAD

Promoter

Builder profile

Builder
OM GROUP OF CIVIL CONTRACTORS AND INFRASTRUCTURES DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100017509
Status
New
Stage
Certificate Signed
Possession
July 2022
Construction
81.8% complete
Units sold
0 of 0