Caution
  • Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 85/1/A/2/1, KUPWAD

Promoter

Builder profile

Builder
SAACHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53100047420
Status
New
Stage
Certificate Signed
Possession
September 2024originally July 2024
Construction
81.8% complete
Units sold
0 of 0