  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 85.9%.
Satellite view of this address

Where it is · SURVEY NO.134/1, Bhiwandi

Promoter

Builder profile

Builder
M/S. INFINI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700008960
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
85.9% complete
Units sold
0 of 0

Similar projects in Bhiwandi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Bhiwandi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.