Omkaar Pride
C.T.S. No. 193A Part, Ghatkopar East, 400075
- Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Jul 2027 per the RERA filing.
- Behind schedule. Possession is due Jul 2027 but construction is only at 47.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Where it is · C.T.S. No. 193A Part, Ghatkopar East
Area guide
What it's like to buy in Ghatkopar East
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Metro-1 anchor with Godrej's Vikhroli land bank next door.
- Growth drivers:
- Metro 1 interchange, Eastern Express Highway, corporate campuses.
- Who buys here:
- Families wanting east-side connectivity to BKC/Fort.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800032084
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2027originally December 2024
- Construction
- 47.5% complete
- Units sold
- 46 of 99
Similar projects in Ghatkopar East
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ghatkopar East compares.
In Ghatkopar East
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.